Guide / 9 minute read

Planned value, earned value and actual cost, the variances and indices, and the common ways to forecast the final cost, with a worked example.

17 October 2026

Earned value tells you two things a plain cost report cannot: whether you are getting the work done that you planned, and whether you are paying more or less than planned for the work you have done. It works by putting the plan, the progress and the cost into the same unit, money, so they can be compared directly.

The three numbers

TermAlso calledWhat it means
Planned value (PV)BCWS, budgeted cost of work scheduledThe budget for the work you planned to have done by now
Earned value (EV)BCWP, budgeted cost of work performedThe budget for the work you have actually done
Actual cost (AC)ACWP, actual cost of work performedWhat the work you have done actually cost

The total budget for the whole job is the budget at completion (BAC). Planned value rises over time from zero to the BAC, which is why it is drawn as an S-curve.

The key idea: earned value uses the budget for the work done, not the money spent. That is what lets you compare progress with the plan and with the cost.

Variances and indices

MeasureFormulaReading it
Schedule variance (SV)EV − PVBelow zero: less work done than planned
Cost variance (CV)EV − ACBelow zero: the work done cost more than its budget
Schedule performance index (SPI)EV ÷ PVBelow 1.0: behind plan
Cost performance index (CPI)EV ÷ ACBelow 1.0: over budget for the work done

A worked example

A job has a budget at completion of £1,000k. At the end of month six:

  • planned value is £400k (the plan said £400k of work would be done);
  • earned value is £350k (the work actually done was budgeted at £350k); and
  • actual cost is £420k (that work cost £420k).

So:

  • SV = 350 − 400 = −£50k, and SPI = 350 ÷ 400 = 0.875. The job is behind plan.
  • CV = 350 − 420 = −£70k, and CPI = 350 ÷ 420 = 0.83. Each pound of work is costing about £1.20.

Forecasting the final cost

The estimate at completion (EAC) is the forecast final cost. There is no single right formula. Each one makes a different assumption about the work still to do, which is why it helps to see several side by side.

MethodFormulaAssumesExample
Remaining work at budgetAC + (BAC − EV)The overspend so far was a one-off£1,070k
Cost performance continuesBAC ÷ CPIFuture work costs what past work did£1,200k
Cost and schedule pressureAC + (BAC − EV) ÷ (CPI × SPI)Being late will also push cost up£1,311k
Bottom-upAC + a new estimate to completeThe team re-estimates the remaining workDepends on the estimate

Two more useful numbers:

  • Variance at completion: BAC − EAC. Using the CPI forecast, 1,000 − 1,200 = −£200k.
  • To-complete performance index: (BAC − EV) ÷ (BAC − AC). Here 650 ÷ 580 = 1.12. To finish on budget, the rest of the work must be done about 12% more efficiently than planned. That is rarely realistic, which is itself a useful message.

How progress is measured

Earned value is only as good as the way progress is claimed. Common methods are:

  • 0/100: no value until the task is finished. Good for short tasks.
  • 50/50: half when it starts, half when it finishes.
  • Weighted milestones: value claimed as agreed milestones are met.
  • Units complete: value in proportion to measured quantities, such as metres laid.
  • Physical percent complete: an assessed percentage, best backed by clear rules.
  • Level of effort: value earned with time, for support work such as management. Keep it small, because it always looks on plan.

Never claim earned value from money spent. If earned value simply follows actual cost, the CPI will always be 1.0 and tell you nothing.

Things to watch

  • SPI drifts back to 1.0 at the end. When all the work is done, EV equals PV, however late the job was. Earned schedule methods, which measure the delay in time rather than money, help late in a job.
  • Work at the right level. Earned value works best at control account level, where one person owns the scope, schedule and budget.
  • Keep the baseline stable. Only approved changes should move the performance measurement baseline, or the variances lose their meaning.

Common references for earned value management include the EIA-748 standard and guidance from the Association for Project Management.

Primer works out earned value at control account level from the same links as the schedule, and shows several forecasts side by side. See Cost in Primer.

This guide is general information, not legal, contractual or financial advice. Always check the source documents for your own contract or company.

Ready when you are

No sign-up. Open a private copy of Primer in your browser. Or take 30 days free for 5 people.

Or start a free trial